¡@¡@FPCC HaiI-Fong Utility Plant, located in Hai-fong area inside
Mai-Liao No. 6 Naphtha Cracking Complex, provides power at 300MW
and 42ata,22ata,14ata,8ata process steam, super-pure water, compressed
air, etc. for the process plants in this area, including oil refinery,
naphtha cracking plant and a number of petrochemical plants.
¡@¡@The basic / detailed design, layout arrangement, P&I diagram
of these 3-unit-500T/H boilers were solely
done by FHI; the pressure parts, steel structure, coal pulverizer
with gear unit and other boiler auxiliary were furnished by FHI
and the commissioning led by FHI. This is the first 500T/H boiler
unit designed and manufactured by Taiwan.
Project Milestones:
| 1997-11-06 |
Signed contract with FPCC for 3 units
of 500T/H boilers. |
| 1998-02-14 |
Started piling and civil works |
| 1998-07-01 |
Steel column standing |
| 1999-08-16 |
Unit 1 Boiler Ignition |
| 1999-11-13 |
Unit 1Commercial running |
| 1999-11-15 |
Unit 2 Boiler Ignition |
| 1999-12-18 |
Unit 2 Commercial running |
| 2000-02-14 |
Unit 3 Boiler Ignition |
| 2000-04-06 |
Unit 3 Commercial running |
|
|
|
FORMOSA PETROCHEMICAL
CORPORATION, HAI FONG HP-1
COGENERATION PLANT,
500T/H x 100MW |
|