FPCC Tauyuan Terminal Phase II Project(Construction in progress)

Area 2.5ha, Floor area 4,000m2, Concrete 6,800KL, Equipment & Storage tank 2,700MT, Piping 45,750DB, Electric wiring 110Km.
Construction started on Feb. 1, 2021. Foundation of the tank excavated on Apr. 8, 2021. Underground piping started on Mar. 29, 2021.