FPCC OL-3 H-101~H-118 Ethylene Cracking Furnace Project

Ethylene Capacity 1.2 mio. -t/a., startup on May,
2007. Quantity of Work:Concrete 11,260KL,
Steel structure 5,438MT, Piping 301,171DB,
Equipment 1,558MT, Electric wiring 132Km,
Refractory 24,924m2.
Convection tube for Incoloy, Alloy, S/S weld bead
for 100% chemical composition analysis (PMI),
to ensure the quality of the weld bead.
Pre-heating and after-heating is performed
when alloy steel tubes are welded.
Pre-heating:
150℃ For SA335-P11
200℃ For SA335-P22
250℃ For SA335-P5、P91
After-heating:
350℃*1Hr
Hardness test after alloy steel pipe PWHT
SA335-P91:HB275
SA335-P5、P22:HB241
SA335-P11:< HB225
Radiation Section Completed
Transition Zone Completed